What should a mains water chlorination method statement include?
A mains water chlorination method statement should define the work scope, responsibilities, hazards and controls, including system isolation, preparation, chemical handling, disinfection steps and protection of users and the environment. It should also specify contact requirements, sampling and testing arrangements, acceptance criteria, contingency measures and the records needed to demonstrate that the work was completed safely and correctly.
A mains water chlorination method statement should be a site-specific, controlled document that explains how the proposed work will be carried out, verified and brought back into service. It should translate the design and risk assessment into a practical sequence, identify the information needed before work starts, and define the evidence required to show that the treated main is suitable for use.
Document control and scope. The document should identify the site, main or section being treated, revision status, author, reviewer, approval arrangements and intended audience. It should state whether the work covers a new installation, an extension, a repaired section or an existing main, and define the physical limits of the work. Drawings, valve schedules, schematic diagrams and relevant specifications should be referenced so that everyone can identify the correct pipework and connection points.
System information. Include the pipe material, nominal size, estimated volume, configuration, storage arrangements and any branches, dead ends, tanks, meters, pumps or fittings that could affect the treatment. The method should explain how the volume has been established and identify sections that cannot be treated by the proposed arrangement. This prevents uncertainty over the quantity of water to be displaced, the location of injection points and the parts of the system requiring separate attention.
Pre-start requirements. A sound method statement should list the conditions that must be met before chlorination begins. These may include completion of installation or repairs, removal of construction debris, access to valves and drain points, confirmation that connected equipment is suitable for the procedure, and agreement of any required isolations. It should also identify any permits, notifications, approvals or coordination with the water undertaker, site operator or affected building users. A clear hold point should be included where the work cannot proceed until these prerequisites have been checked and recorded.
Detailed work sequence. The procedure should set out the order of operations rather than simply stating that the main will be disinfected. It should describe how the system will be prepared, how treatment water or disinfectant will be introduced, how it will be distributed through the relevant pipework, and how displaced water will be controlled. The sequence should cover valve operation, flushing routes, drain-down arrangements and any points where the work must pause for inspection or confirmation.
Where the process uses a chemical disinfectant, the document should state the product specification, required concentration or dosing basis, preparation method, equipment used and means of confirming the solution strength. It should explain how chemical compatibility has been considered for pipework, seals, fittings and connected equipment. Safety data should be available for the product, with instructions for storage, handling, labelling, spill control and disposal. The method should not rely on informal decisions about chemical quantities or application.
Flushing and reinstatement. The method statement should explain how treated water and any residual disinfectant will be removed, where discharge will take place and how the receiving drainage or environment will be protected. It should set out how the main will be flushed with suitable water, how valves and outlets will be returned to their normal configuration, and how the system will be checked before reconnection. If there are restrictions on discharge, these should be addressed before the work begins rather than left to the site team to resolve during the operation.
Verification arrangements. The document should define the sampling plan in enough detail to make the results meaningful. It should identify sample points, the order in which samples will be taken, the tests required, sample preservation and transport arrangements, and the laboratory or competent testing service to be used. It should state how results will be assessed against the agreed acceptance requirements and who is authorised to release the main for use. A result that cannot be linked to a named location, date, stage of the process and relevant section of pipework provides weak evidence of completion.
Interfaces and site coordination. Mains chlorination often affects other activities, so the method statement should identify interfaces with excavation, construction, commissioning, building management and operational teams. It should explain how the treated main will be distinguished from live or untreated pipework, how unauthorised use will be prevented during the process, and how the completion status will be communicated. Signage, tagging and controlled access may be appropriate where confusion could expose users to untreated or chemically affected water.
Completion evidence. The method statement should identify the records that will be generated as the work proceeds, such as pre-start checks, equipment checks, dosing records, field observations, test results, deviations and approval of reinstatement. It should also state how changes to the agreed method will be authorised and documented. The method statement is not a substitute for the final completion report; instead, it should make clear what information the report must contain so that the work can be audited afterwards.
Before approval, the document should be reviewed against the actual site layout and current project conditions. A generic procedure may omit a branch, inaccessible valve, sensitive item of equipment or discharge constraint. The most useful method statements are therefore concise enough to follow on site but specific enough to remove uncertainty about the pipework, treatment sequence, controls, verification and handover.

A robust mains water chlorination method statement should define the response to an unsatisfactory, inconclusive or invalid test result. It should state that the treated section remains out of service, identify who reviews the result, and set out the permitted corrective steps, such as investigating the affected section, repeating flushing or carrying out further treatment before re-sampling.
This decision route prevents a main being released on the basis of an unclear result or an informal judgement. It should also specify how failed results, additional work and the final release decision are recorded, creating a clear link between the test evidence and the decision to return the main to service.